A375 Vicarage Road, Temple Street, Radway Update


Trial Pits were taken last Friday evening 30th April on the A375 Vicarage Road and lower section of Temple Street for the Materials Lab to establish the extent of the foundation problem which has failed at regular periods and dates back over 50 years ago.

It had been hoped to have resurfaced / reconstructed this the busiest road into Sidmouth in February, however the problem was identified.

Now technician engineers are working up the exact scheme required to ensure this problem is sorted once and for all and it looks more likely Geogrids will be required to bind the foundations before overlay is carried out and the estimated cost is in the region of over £1m .... Work will be programmed so not to disrupt Sidmouth Town Centre traders as we continue to come out of lockdown.


26 views0 comments

Recent Posts

See All

Road users are being urged to take extra care on Devon’s roads from tomorrow afternoon (Wed 27 Sept) with the Met Office forecasting the possibility of disruption from the first named storm of this au

The Lead for Seasonal Vaccination Programme Operations and Workforce for Devon ICB has kindly provided an update. That they are planning outreach activities that will include a number of clinics in th

bottom of page